We have completed the church! A group of 19 worked to lay flooring, trim, hang lights and paint. Thanks to all that helped! The carpet is being installed in the next few days but that did not stop Christian Valley from having their first service in the new building.
Thursday, March 15, 2012
Job well done
We have completed the church! A group of 19 worked to lay flooring, trim, hang lights and paint. Thanks to all that helped! The carpet is being installed in the next few days but that did not stop Christian Valley from having their first service in the new building.
Saturday, March 3, 2012
Saturday, February 25, 2012
Saturday, February 18, 2012
02/18/2012
Foundation. Check
Framed check
Insulated check
Wired check
Heat check
Plumbing check
Brick. Check
Roofing soffit. Check
Drywall hung. Check
Tired people. Check
What an amazing two weeks.
Thanks to all who helped so far. Each one was needed. Ten church members were there this evening and their smiles said it all!
We leave here having made new friends
In two weeks we will be back down to finish the church
Framed check
Insulated check
Wired check
Heat check
Plumbing check
Brick. Check
Roofing soffit. Check
Drywall hung. Check
Tired people. Check
What an amazing two weeks.
Thanks to all who helped so far. Each one was needed. Ten church members were there this evening and their smiles said it all!
We leave here having made new friends
In two weeks we will be back down to finish the church
Friday, February 17, 2012
New Pictures
There are a few new pictures in the link below, theres one of the church after it was hit by the torando! clickhere
Ray and Marty Troyer 02/16/2012
Monday, February 13, 2012
Friday, February 10, 2012
Pictures!
Sorry there has been no pictures, the internet access down here is minimal to none. Chris uploaded the pics to a web link.... click here!
Monday, February 6, 2012
Saturday, February 4, 2012
02/04/2012 Framing
We have started framing. On Thursday 6 on us drove down here to set up camp, make sure we could get NBC to watch the Super Bowl and start framing. Today the rest of our group starting arriving and a few more will be coming tomorrow. Friday forenoon was nice but then turned into light rain. Today's weather was great, well at least while working. We quit around 3:00 and by 4 it was raining hard. Our shower trailer is working out great and the washer and dryer were put to use after working in the rain.
Hopefully we have made our last trip to Demopolis for supper as our cooks have arrived!
Saturday, January 14, 2012
A firm foundation
The foundation is complete! 
Blaine Miller and Scott Troyer traveled down January 4Th, pulling the
newly built shower trailer. They worked Thursday, Friday and Saturday, leveling the site, digging the footer and clearing many downed trees.
Monday morning they were joined by Glenn Coblentz, Eric Worland, JJ Robertson, Rick Miller and Tyler Miller to do concrete and Perry Miller and Dan Dutcher to do plumbing.

The footer was poured by 11:00, plumbing and septic happened in the afternoon along with prepping for the floor.
Tuesday came with lots of rain, so pouring the floor was put off until Wednesday and a concrete pumper was needed as the site got very muddy after the rain.
Blaine Miller and Scott Troyer traveled down January 4Th, pulling the
Monday morning they were joined by Glenn Coblentz, Eric Worland, JJ Robertson, Rick Miller and Tyler Miller to do concrete and Perry Miller and Dan Dutcher to do plumbing.
The footer was poured by 11:00, plumbing and septic happened in the afternoon along with prepping for the floor.
Tuesday came with lots of rain, so pouring the floor was put off until Wednesday and a concrete pumper was needed as the site got very muddy after the rain.
Monday, January 2, 2012
Shower trailer
Sunday, January 1, 2012
A new project
Several Hartville area Mennonite Churches are joining together to rebuild the Christian Valley Church building in Boligee Alabama. It was destroyed by a tornado on April 27 2011. The building is 5000 sq ft, L shaped. The exterior will be bricked.
Our weekly schedule is
January 9, Foundation
February 6, Framing
February 13, Wire, insulating and brick
February 20 Drywall
February 27 Drywall
March 5, Paint and Trim
We will be using the Little Zion Baptist Church for meals and lodging. A side note; Little Zion was rebuilt after the racial fires in 1996, with the help of Mennonites.
Our weekly schedule is
January 9, Foundation
February 6, Framing
February 13, Wire, insulating and brick
February 20 Drywall
February 27 Drywall
March 5, Paint and Trim
We will be using the Little Zion Baptist Church for meals and lodging. A side note; Little Zion was rebuilt after the racial fires in 1996, with the help of Mennonites.